Schedule:

Approx Date

Objective completed

July 5 Background research should be complete, should be ready to plan some an implementation
July 15 Implementation planning should be about complete
July 18 Project Design should be complete
July 30 Coding should be wrapping up
Aug 5 Testing should be complete, Begining to wrap up the class project, while maintaining development in OSS community
   
DONE at this point the class is done, but the project will continue.